Playbook · Delivery

Sprintplanning

How to turn a refined backlog into a committed sprint goal and a sprint backlog sized to the team's real capacity.

When to use

Hold sprint planning on the morning of day 1 of every sprint, once the top of the backlog has been refined.

Roles

  • Product Owner: brings the ordered backlog and proposes the sprint goal.
  • Scrum Master: facilitates and keeps the session to its timebox.
  • Developers: decide how much work fits, plan how to do it and commit to the sprint backlog.
  • Project Manager (on strategic projects): joins the first half hour to confirm how the sprint goal moves the next milestone, and to flag dependency dates.

Before you start

  • Make sure about two sprints of ready items sit at the top of the backlog.
  • Work out the team's capacity for this sprint. Account for leave, holidays and on-call duty. Take the team's average velocity over the last three sprints as a guide.
  • Check the milestone plan, so you know what this sprint must contribute.

Steps

  1. Set the context. In 5 minutes, the Product Owner restates the next milestone and says what was learned at the last sprint review.
  2. Propose a sprint goal. The Product Owner proposes one goal for the sprint, in a single sentence that states an outcome, such as "Agents can see a quote's status without calling us".
  3. Choose the items. Take ready items from the top of the backlog that serve the goal, until the team's capacity is reached. Leave about 10% free for refinement and surprises.
  4. Plan the work. Developers break each item into tasks of a day or less. If an item turns out larger than it looked, say so now and drop or split it.
  5. Check dependencies. Confirm that every dependency this sprint relies on is agreed. The Project Manager follows up on any that aren't.
  6. Agree the goal. Re-read the sprint goal against the chosen items. Adjust the wording until the whole team agrees it is achievable.
  7. Commit and publish. Publish the sprint goal and the sprint backlog where stakeholders can see them, such as the team board or channel.

Outputs

  • A sprint goal everyone can say in one sentence.
  • A sprint backlog sized to the team's real capacity, with tasks for the first few days.

Pitfalls

  • Planning to 100% capacity. That leaves no room for Run work, incidents or anything learned during the sprint.
  • A goal that is just a list of items. "Finish items 101 to 108" isn't a goal. Say what will be different for a user or the business.
  • Pulling in unready items. If an item doesn't meet the Definition of Ready, it goes back to refinement, not into the sprint.