High-leveldesign review

How to agree a high-level design for an accepted idea, so it can be estimated and prioritized with confidence.

When to use

Use this playbook after an idea passes Gate 1. The aim is a design just detailed enough to size the work and see its risks. It isn't a full technical specification.

Roles

  • Product Manager: leads. You own the problem statement and the outcome the design has to reach.
  • Senior engineer or architect from the main affected platform: drafts the design.
  • Program Manager: checks dependencies on other projects and on shared platforms.
  • Product Owners of the affected Home Teams: check the design against what their backlogs and platforms already do.

Before you start

  • Make sure the business case passed Gate 1, and have it to hand.
  • Ask each affected Home Team for 1 to 2 hours of a senior engineer's time.
  • Collect recent Platform Health findings for the platforms involved, because known reliability problems change the design.

Steps

  1. Restate the outcome. Open the design document with the problem and the measure of success from the business case.
  2. Sketch the options. Describe two or three ways to reach the outcome, each in a short paragraph and a simple diagram. Include doing less, such as a manual or process change.
  3. Pick a recommended option. Say why, in terms of the outcome, cost and risk.
  4. Name what changes. List each platform, integration and Home Team the recommended option touches, and anything that must be retired.
  5. List risks and unknowns. Mark each as design, delivery or business. Suggest a spike for any unknown big enough to change the size.
  6. Hold the review. In 60 minutes, walk through the outcome, the options and the recommendation, then spend most of the time on risks.
  7. Record the decision. Choose one:
    • Approved: move on to T-shirt estimation.
    • Approved with spikes: time-box the spikes to one sprint, then estimate.
    • Rework: fix the gaps the review named and review again.

Outputs

  • A high-level design of 3 to 5 pages: the outcome, the options, the recommendation, what changes, and risks.
  • A list of affected Home Teams. Planning uses it to form the project team.
  • Open risks with an owner each.

Pitfalls

  • Designing in full detail. Detailed design happens in Delivery, inside sprints. Here you need just enough to size the work.
  • One option only. Without alternatives, nobody can tell whether the recommendation is the right one.
  • Missing a Home Team. Every team you forget becomes a surprise dependency in Delivery.