How to give a reviewed design a T-shirt size from XS to XL that Planning can turn into team capacity.

When to use

Use this playbook once an idea has an approved high-level design. A T-shirt size is a rough range, not a commitment. It gives portfolio prioritization something to weigh value against, and gives Planning a starting point for capacity.

Roles

  • Program Manager: leads. You facilitate the session and keep sizes consistent across the portfolio.
  • Product Manager: explains the outcome and answers scope questions.
  • Product Owners and senior engineers from the affected Home Teams: do the estimating.

The size scale

We count sizes in team-sprints: one team for one two-week sprint.

Size Team-sprints What it usually looks like
XS 1 or fewer A change one team can finish in a sprint
S 2 to 3 One team, a few sprints, no other teams involved
M 4 to 6 One team for about a quarter
L 7 to 18 Two or three teams for about a quarter
XL More than 18 Several teams or more than a quarter. Split it before Gate 2

Work of size S or smaller that stays within one Home Team is usually Discretionary, not a strategic project.

Before you start

  • Send the high-level design to the estimators two working days ahead.
  • Bring two or three past projects with known actual sizes to use as reference points.

Steps

  1. Walk through the design. The Product Manager spends 10 minutes on the outcome and the recommended option.
  2. Estimate silently. Each estimator picks a size on their own and writes it down.
  3. Reveal together. If everyone agrees, record the size and skip to step 5.
  4. Discuss the spread. Ask the highest and lowest estimators to explain their thinking. Re-estimate once. If the group still disagrees, record the larger size and note the disagreement as a risk.
  5. Write down the assumptions. List what the size depends on, such as "reuses the existing claims API" or "no data migration".
  6. Split XL work. If the size is XL, propose how to split it into projects of L or smaller, each with its own outcome. Each part goes through prioritization separately.
  7. Record the result in the idea log: the size, its team-sprint range, the assumptions and the date.

Outputs

  • A T-shirt size and its team-sprint range.
  • A list of assumptions behind the size.
  • For XL ideas, a proposed split into L or smaller projects.

Pitfalls

  • Treating a size as a deadline. Dates come from Planning, after capacity is known.
  • Anchoring. If someone says a number before the silent estimate, the group tends to follow it.
  • Forgetting Run work. Team-sprints are for Change work only. Planning sets aside the Run allowance separately.