Resource andcapacity planning

How to work out each Home Team's capacity for the quarter, protect the Run allowance and staff the projects that passed Gate 2.

When to use

Run this once a quarter, starting four weeks before the quarter begins, straight after the final portfolio prioritization. Rerun steps 3 to 6 mid-quarter if a project is added, stopped or loses people.

Roles

  • Program Manager: leads. You build the capacity plan and make the staffing proposal.
  • Product Owners of each Home Team: confirm team capacity, the Run allowance and the Discretionary share.
  • Project Managers: review the proposed project team for their project and flag missing skills.

Before you start

  • Get the ranked portfolio list with the projects that passed Gate 2, their T-shirt sizes and their affected Home Teams.
  • Collect each Home Team's roster, planned leave and on-call rota for the quarter.
  • Check Platform Health findings. A platform with open reliability problems may need a larger Run allowance.

Steps

  1. Count each Home Team's capacity. A quarter is 6 sprints, so a full team has 6 team-sprints. Reduce that for planned leave, holidays and new starters.
  2. Take out the Run allowance. Our default is 20% of each Home Team's capacity for Incident Management and Platform Health. Raise it for any platform with open reliability findings. Don't lower it below 10% without the Product Owner's agreement.
  3. Reserve the Discretionary share. Agree with each Home Team's Product Owner how much of the rest goes to their own backlog. Keep at least 1 team-sprint per Home Team, so small improvements don't stop.
  4. Offer the rest to projects. Go down the ranked list and assign capacity to each Gate 2 project, using the middle of its T-shirt range. Note which Home Teams each project draws on.
  5. Form project teams. For each project, propose named people from the affected Home Teams. Each project team needs a Product Owner and a Scrum Master, plus the skills the design calls for. Check each proposal with the Project Manager.
  6. Mark what doesn't fit. If a project can't be staffed, flag it as unstaffed. Don't spread people across more projects to make it fit.
  7. Publish the capacity plan to Project Managers, Product Owners and Product Managers so milestone planning can start.

Outputs

  • A capacity plan per Home Team: total team-sprints, the Run allowance, the Discretionary share and the project allocation.
  • A proposed roster for each project team.
  • A list of unstaffed projects to raise at Quarterly Planning.

Pitfalls

  • Planning to 100%. People also do support, training and hiring. The Run allowance covers Run work only.
  • Splitting people across too many projects. Someone on three projects makes progress on none. Aim for one project per person, two at most.
  • Quietly dropping the Run allowance. When incidents arrive, they take the time anyway, and the project plan slips without anyone deciding it should.